New double garage extension build
#1
PassionFord Post Troll
Thread Starter
New double garage extension build
Going to be an ongoing project for me, basically bought our bungalow in May last year and wasted no time in submitting a planning application for a new double garage extension. The new garage dimensions will be 6.2m wide and 5.9m deep. (20ft 4" x 19ft 4") Garage will be double skinned and insulated, insulated 14.5ft automated sectional door with double glazing to match existing doors on the development. Also have composite rear door and a window.
also got permission to install velux window as in the future i would like to put another ensuit bedroom up there in the new space. once the garage is done i will be submitting a change of use application of the old garage, this will be to create a new dining room and have access to a new bedroom above the new garage.
The idea was to start the project around October/November time after building consent was given in September.
Also consent was needed off the highways agency as i need to drop 9 kerbs to gain access to the new garage. There will be a small gradient going into the garage.
There was a few small jobs to do first and the really bad weather delayed things a little so gave me an opportunity to sort them out.
The bungalow and proposed site attached to the existing garage :
also got permission to install velux window as in the future i would like to put another ensuit bedroom up there in the new space. once the garage is done i will be submitting a change of use application of the old garage, this will be to create a new dining room and have access to a new bedroom above the new garage.
The idea was to start the project around October/November time after building consent was given in September.
Also consent was needed off the highways agency as i need to drop 9 kerbs to gain access to the new garage. There will be a small gradient going into the garage.
There was a few small jobs to do first and the really bad weather delayed things a little so gave me an opportunity to sort them out.
The bungalow and proposed site attached to the existing garage :
#2
PassionFord Post Troll
Thread Starter
One of the first jobs was to create another gateway to gain access to the rear of the property, got this gate given So fitted it on the opposite side of bungalow.
Also the combi boiler was situated in the existing garage and the flue was venting out of the gable end where the new garage will be built. Anyway the boiler packed in and gave up the ghost so the perfect opportunity arose to relocate it to the other end of property where the 2 bathrooms are.
It took ages to get the hot water to the bathrooms and was never really boiling hot as it travelled a long distance. So got a new higher powered boiler fitted in the loft directly above where the 2 bathrooms are. Result, instant hot water and not using a fraction of water (on a meter)
Also the combi boiler was situated in the existing garage and the flue was venting out of the gable end where the new garage will be built. Anyway the boiler packed in and gave up the ghost so the perfect opportunity arose to relocate it to the other end of property where the 2 bathrooms are.
It took ages to get the hot water to the bathrooms and was never really boiling hot as it travelled a long distance. So got a new higher powered boiler fitted in the loft directly above where the 2 bathrooms are. Result, instant hot water and not using a fraction of water (on a meter)
#3
PassionFord Post Troll
Thread Starter
So eventually a break in the weather this week 10th Feb i decided it was time to start the project. Firstly the site would have to be cleared away and wall removed. Approximately about 100 tonne of rubble to be removed.
Put up a temporary SON light just in case light was an issue through winter (didn't matter in end)
Put up a temporary SON light just in case light was an issue through winter (didn't matter in end)
#4
PassionFord Post Troll
Thread Starter
So with area cleared time to dig the founds out. Had to locate the original founds of bungalow first, 3 courses of engineered bricks and 4 courses of blocks we found the foundations, they were nearly 2ft deep !!!!!!
Became quite apparent these were going to be substantial diggings going on. Ended up in total going down 7ft to find solid ground.
Not only that we had to go through a massive slate deposit and huge chunks of slate.
Became quite apparent these were going to be substantial diggings going on. Ended up in total going down 7ft to find solid ground.
Not only that we had to go through a massive slate deposit and huge chunks of slate.
#5
PassionFord Post Troll
Thread Starter
So at 14:30 digging stopped and i made a call to the building control inspector, he arrives at 15:00 and passes them off. I make a quick call to the local village concrete suppliers and an hour later at 4pm it looked like this, poured directly in to the desired height. Founds ended up 2ft deep as the same as the bungalow.
#6
PassionFord Post Troll
Thread Starter
So thats it for time being as my brickie friend will start building in a couple of weeks time. I will be helping out as much as i can and hopefully once the facing bricks and blockwork is done i can bash on with it in my own time.
Trending Topics
#8
Too many posts.. I need a life!!
nice job
do it right and do it once!
do it right and do it once!
The following users liked this post:
S3an (18-02-2016)
#10
PassionFord Post Troll
Will keep an eye on this mate love the size of your garden I'm well jealous lol. Also the boiler pipe work looks pretty neat.
I've only got a 14'x8' garage just now and I'm planning on flattening it in the future to build a bigger double garage but unfortunately I don't have quite as big a garden as you lol.
I've only got a 14'x8' garage just now and I'm planning on flattening it in the future to build a bigger double garage but unfortunately I don't have quite as big a garden as you lol.
#11
PassionFord Post Troll
Thread Starter
Been getting all materials delivered to site this week in prep for builder starting next weekend, had 2 decorative corner stones hand casted to match original ones. Had to do the radon checks as well. Bought other odds and sods this weekend, such as 2.5mm twin and earth cable, on offer 100 metres of cable from screwfix only Ł37.
#15
#16
PassionFord Post Troll
Thread Starter
Just a little update, this week saw a lot of back filling.
Levelled ground off 13" below floor height. All by hand, no machinery. Except the whacker.
Got a delivery of 10 tonne class 1 hardcore
Whackered it all down ready for the sand to go on
Sand covering leaving 6" for concrete
DPM in and reinforcing mesh down, shuttering up front
Concrete poured in
Levelled ground off 13" below floor height. All by hand, no machinery. Except the whacker.
Got a delivery of 10 tonne class 1 hardcore
Whackered it all down ready for the sand to go on
Sand covering leaving 6" for concrete
DPM in and reinforcing mesh down, shuttering up front
Concrete poured in
The following users liked this post:
H3lsing (19-03-2016)
The following users liked this post:
S3an (22-03-2016)
#19
Too many posts.. I need a life!!
This is going really well and is looking really impressive. Keep up the good work and keep on updating.
Isnt it weird how a garage build is getting us men excited
Isnt it weird how a garage build is getting us men excited
The following users liked this post:
S3an (31-03-2016)
#22
PassionFord Post Troll
Thread Starter
Another washout this weekend, maybe get summet done tomorrow. All this bad weather means getting inside jobs done so not to bad.
#23
PassionFord Post Troll
Thread Starter
So a little progress on the garage, getting nearly up to scaffold height now, hopefully get some done this weekend. There's been a bit more done since these pics.
And I managed to get some spare time on the ensuite to get it finished, before and after pics:
And I managed to get some spare time on the ensuite to get it finished, before and after pics:
Last edited by S3an; 08-04-2016 at 11:17 PM.
The following users liked this post:
H3lsing (09-04-2016)
#24
PassionFord Regular
looking great this, hope ya get some decent weather to crack on with it.
Last edited by andy.v; 09-04-2016 at 08:24 PM.
#27
PassionFord Post Troll
Thread Starter
So had some progress this week, we are now up to wall plate height, attic trusses are designed and getting ordered on Monday after a quick visit from the wood yard to check sizes.
The 4.8 mtr catnic CX90 extra heavy duty lintel was a heavy thing to lift up. Beast of a thing. The blocks on the front were just to counter balance the weight of the blocks on the back.
The 4.8 mtr catnic CX90 extra heavy duty lintel was a heavy thing to lift up. Beast of a thing. The blocks on the front were just to counter balance the weight of the blocks on the back.
Last edited by S3an; 23-04-2016 at 09:43 PM.
#31
PassionFord Post Troll
Thread Starter
Just quick prices so far:
Building, planning consent: Ł185
Building control: Ł440
New 14.5ft door: Ł1850
Composite door: Ł500
Window: Ł100
Highways consent for drop kerbs: Ł230
Land clearance and prep: Ł800
Blocks,bricks,cement etc appx: Ł2500
Readymix concrete 12 cubic mtrs: Ł1000
3x heavy duty lintels: Ł450
5x large bags building sand: Ł165
Scaffold: Ł300
Velux, probably another 2 though: Ł200
Builder if was paying him: Ł2000
AtticTrusses load bearing x16: Ł2100
9x drop kerbs and new driveway: Ł1800
channel drainage: Ł150
Fascias,drainpipes etc not sure
new 5tonne rating manhole cover:Ł120
Roof,ridge and cloke tiles, lats. Ł600
Reinforcing bar meshx4 sheets: Ł120
2x handcrafted corner stones: Ł120
10 tonne class 1 hardcore: Ł150
Probably other little stuff ive forgotten.
So probably some where in region of Ł13000 there. So realistically with other stuff not known yet i would say some where close to the Ł15k region.
ive done quite a lot of work on it myself and will continue to do so.
Ive tried to keep costs down but things are so expensive to buy now.
I have no doubt it could have been done cheaper, doors etc.
Building, planning consent: Ł185
Building control: Ł440
New 14.5ft door: Ł1850
Composite door: Ł500
Window: Ł100
Highways consent for drop kerbs: Ł230
Land clearance and prep: Ł800
Blocks,bricks,cement etc appx: Ł2500
Readymix concrete 12 cubic mtrs: Ł1000
3x heavy duty lintels: Ł450
5x large bags building sand: Ł165
Scaffold: Ł300
Velux, probably another 2 though: Ł200
Builder if was paying him: Ł2000
AtticTrusses load bearing x16: Ł2100
9x drop kerbs and new driveway: Ł1800
channel drainage: Ł150
Fascias,drainpipes etc not sure
new 5tonne rating manhole cover:Ł120
Roof,ridge and cloke tiles, lats. Ł600
Reinforcing bar meshx4 sheets: Ł120
2x handcrafted corner stones: Ł120
10 tonne class 1 hardcore: Ł150
Probably other little stuff ive forgotten.
So probably some where in region of Ł13000 there. So realistically with other stuff not known yet i would say some where close to the Ł15k region.
ive done quite a lot of work on it myself and will continue to do so.
Ive tried to keep costs down but things are so expensive to buy now.
I have no doubt it could have been done cheaper, doors etc.
Last edited by S3an; 15-05-2016 at 09:59 PM.
#32
PassionFord Post Troll
Thread Starter
#34
Too many posts.. I need a life!!
looking good mate. could you not get different attic trusses so that you could use that space better?
#35
PassionFord Post Troll
Thread Starter
That's not the actual trusses getting made, previous post states it was a sample to check the sizes before making the propper ones.
Last edited by S3an; 16-05-2016 at 07:04 PM.
The following users liked this post:
salsheikh (16-05-2016)
#37
Advanced PassionFord User
Great build , but I would be tempted to run 3 rsj from outside wall mounted into original house wall that way you could have full height use in the garage and maybe a ramp
It's just a waste of a good space , keep up the good work
Cheers paul
It's just a waste of a good space , keep up the good work
Cheers paul
#38
PassionFord Post Troll
Thread Starter
The plan is to have another ensuite bedroom up there, convert the original single garage into a dining room with a spiral staircase going up into the new living space.