Domestic Main Electric Question.....
#1
Thread Starter
#1 in Spelling Club
iTrader: (14)
Joined: May 2003
Posts: 23,329
Likes: 6
From: Norfolk
Domestic Main Electric Question.....
We have to get our Electric Main moved, for various reasons, but its a bit of a conundrum. We plan to build a detached Garage that will stand fairly close to the Electric pole that our mains cable comes in on, before it passes over the top of our garden and to our Bungalow.
Now, because the new Garage will be close to the pole (although entirely detached and separate from the Bungalow), is it acceptable for the Electric Main to come off the pole and into the new Garage, with the Meter there, then from there, to the Consumer Unit in the Bungalow (probably underground)? I imagine it would be, but someone on here must have some clue?
Now, because the new Garage will be close to the pole (although entirely detached and separate from the Bungalow), is it acceptable for the Electric Main to come off the pole and into the new Garage, with the Meter there, then from there, to the Consumer Unit in the Bungalow (probably underground)? I imagine it would be, but someone on here must have some clue?
#4
16mm armoured cable is around £5 per metre so you can work out your costs for that as you would need to run this from your meter to your consumer unit. Then you just want a price from the supplier for relocating you metre to your garage.
#6
Gonna be cheaper to run a supply from ya house to garage than other way round chap
They will give a price for altering it but sit down first before you read final figures from them,ya sparky and bloke digging trench (tho you will need one anyway)
Good luck
They will give a price for altering it but sit down first before you read final figures from them,ya sparky and bloke digging trench (tho you will need one anyway)
Good luck
#7
They'll probably want an external meter box fitting, and you'll have to have your own isolator in the garage which you can then use to split a feed to the bungalow and new consumer unit for the garage.
I'd guess that the cost of installing new supply, removing old overheads, relocate meter in a box supplied by you and then your costs to re-feed your existing consumer unit are going to get close to £3k.
But you'd still have to feed the garage from the bungalow if you didn't move the incomer.
.
.
I'd guess that the cost of installing new supply, removing old overheads, relocate meter in a box supplied by you and then your costs to re-feed your existing consumer unit are going to get close to £3k.
But you'd still have to feed the garage from the bungalow if you didn't move the incomer.
.
.
Trending Topics
#8
Thread Starter
#1 in Spelling Club
iTrader: (14)
Joined: May 2003
Posts: 23,329
Likes: 6
From: Norfolk
Well, put it this way. The supply comes in from the pole to our Fascia currently and passes over the top of where we plan to build the garage. We need it off the Fascia as we plan to get those done too, so we have to have a go with EDF Energy in terms of having the supply moved. So, we had them round a year or so ago and based on us laying the conduit underground and either running the cable through it, or putting a chaser in there, so all they have to do is take the overhead cable down and connect the new one at each end via the underground conduit we had already laid, they were talking hundreds, not thousands.
Essentially, what I'm after here is, instead of running the new supply cable all the way to the Bungalow, running it only to the Garage, which is approximately 10 feet from the pole, not 30-40 feet to the Bungalow. I assume that they would connect it to the new meter, which can be in an external box if needed, but in the Garage (or outside it), then I can deal with the wiring from the new Meter (using a normal domestic Sparky), by way of armoured cable (in conduit or not) to the Bungalow.
In my mind, it sounds like an equal amount of work for them, if not less. It's certainly less cable that they would have to supply. Does that make more sense?
Essentially, what I'm after here is, instead of running the new supply cable all the way to the Bungalow, running it only to the Garage, which is approximately 10 feet from the pole, not 30-40 feet to the Bungalow. I assume that they would connect it to the new meter, which can be in an external box if needed, but in the Garage (or outside it), then I can deal with the wiring from the new Meter (using a normal domestic Sparky), by way of armoured cable (in conduit or not) to the Bungalow.
In my mind, it sounds like an equal amount of work for them, if not less. It's certainly less cable that they would have to supply. Does that make more sense?
#9
Some silly figures being posted but i guess it depends on supplier. We did an extension 2 years ago, this was overhead fed and to the gable. The meter was put into a new cavity box that we built in on the new gable and they charged £650, this included mounting the meter and altering the cables.
#10
Some silly figures being posted but i guess it depends on supplier. We did an extension 2 years ago, this was overhead fed and to the gable. The meter was put into a new cavity box that we built in on the new gable and they charged £650, this included mounting the meter and altering the cables.
There's was a cost involved in you fitting and supplying the box, I assume.
Just as there is also a cost in digging a trench, laying the duct, installing a cable to the bungalow and connections each end.
The basic cost will depend on whether EDF want to call it a new supply or not.
.
#13
Some silly figures being posted but i guess it depends on supplier. We did an extension 2 years ago, this was overhead fed and to the gable. The meter was put into a new cavity box that we built in on the new gable and they charged £650, this included mounting the meter and altering the cables.
That is VERY cheap ! they deffo know how to charge usually, most ive seen for a domestic 3 phase supply was £35,000
#16
#17
Switched Isolator at the side of the meter and the jobs jobbed. Run any length of suitable cable from there then to the consumer unit.
#18
fuck me if you are thinking of paying those prices
when we had out meter moved from one wall to the other, including them coming out and shutting the power down, moving the meter from one wall to the other, putting up new boards and all that sort of shit, we paid £30 so where these prices are coming from i have no idea
ok, so we only moved it from one wall to another in the same room, the bit under the stairs had a wooden partition and we took it off that and put it onto the brickwork
perhaps it's different up north but we had ours done by southern electric who we were with at the time
i'll try and find the bill but we'd already had the extension built and all the wiring was ready to go, just needed to move the meter and refit the fusebox and then get them to power up the main box, then run power to the second one, 4 feet away and we were thinking it was going to cost millions but they said there was a basic price to move a meter and it was £30
mind you, this was only about 5 years ago
when we had out meter moved from one wall to the other, including them coming out and shutting the power down, moving the meter from one wall to the other, putting up new boards and all that sort of shit, we paid £30 so where these prices are coming from i have no idea
ok, so we only moved it from one wall to another in the same room, the bit under the stairs had a wooden partition and we took it off that and put it onto the brickwork
perhaps it's different up north but we had ours done by southern electric who we were with at the time
i'll try and find the bill but we'd already had the extension built and all the wiring was ready to go, just needed to move the meter and refit the fusebox and then get them to power up the main box, then run power to the second one, 4 feet away and we were thinking it was going to cost millions but they said there was a basic price to move a meter and it was £30
mind you, this was only about 5 years ago
#20
i would think that, in this case, wouldn't it be easiest to wire everything up and then just leave the electric company to come and hook up the mains and move the meter?
or would that leave them without power while they demolished the rest of the property?
or is this now against elf and safety?
or would that leave them without power while they demolished the rest of the property?
or is this now against elf and safety?
#21
Very right
Thread
Thread Starter
Forum
Replies
Last Post
wowk
General Car Related Discussion.
4
30-03-2021 07:49 PM