Originally Posted by
Lee Ivatt
Not a straight foward answer really, depends a lot on the site and design!
As a rule
200 blocks a day
or
1250-2000 bricks.
tho they have done 3000 before on a straight run.
to give an idea 10 blocks is about 1 m2
200 blocks a day for a 2 and 1 gang? Are you serious ? Before throwing the trowel in ( boom boom lol ) and going into business i used to lay anything between 3 and 6 hundred blocks a day on my own with a labourer! If thats all they are doing they arent worth 500 quid. The bricks amounts fine though

but blockwork is where i made most money....11 quid a meter