Update
Right finally we've had 2 great days of weather and jeffs been cracking on with it . He's started to get the gable walls up and mounted the pad stones up.
Some pics
Brick detail above the door
Today after Jeff got the gables up and pad stones mounted I hired a genie lift to get the x3 6 metre steels up mounted onto the pad stones. Went very well and we took our time so n mishaps.
You can see the top steel
Me and my lad mounted the timbers on the steels , a 1 hour job turned into a 3 hour job he was a nightmare but he enjoyed himself bless him he's only 2 1/2 years old lol.
Over hung the steel slightly half way into the insulation on both sides
Ordering 28 roof joists 47mm x 125 mm (5x2)
200 metres of rafts 25mm x 50mm
650 Marley mendip old English dark red roof tiles
16 Marley ridge tiles old English dark red
8 wall straps 1000mm x 100mm bend
Hopefully that will be it apart from fascia , guttering , soak away and then rendering which I may start the top half before scaffold comes down.
Will update when there's more to show
Cheers paul